This photo was taken May 15, 1977
of vanadium build up on screen tubes at the time a
fuel conditioning system was installed. Note the
vanadium build up that covers the air passage between
tubes restricting heat transfer and increasing excess
air pressure in combustion chamber.
|
|
This photo was taken August
16, 1977. Note the removal of vanadium during operation,
increasing heat transfer and reducing excess air pressure.
|
|
This photo was taken
September 27, 1977. Note the continued removal of vanadium during
operation. There was no mechanical removal of vanadium during this
time.
|